Kab. Morowali

Progres Per 11 November  2011

Progres Kegiatan Optimalisasi Kab. Morowali Sul-teng

No. Uraian Kegiatan JADWAL PELAKSANAAN
Ket.
Rencana [tgl-bln-thn] Realisasi[Tgl-Bln-Thn] Deviasi
Mulai Selesai Mulai Selesai
TAHAP PERENCANAAN
I Musyawarah Kabupaten I
a Persiapan Forum MKab-I 07/11/2011 17/07/2011 18/07/11 18/07/11 10H Sdh
b Konsolidasi 01/07/2011 06/07/2011 06/07/2011 08/07/2011 2H Sdh
c Forum MKab-I 11/07/2011 11/07/2011 18/07/2011 18/07/2011 7H Sdh
II Penyusunan Disain dan RAB
a Persiapan [seleksi dan pelatihan] 19/07/11 19/07/11 19/07/11 19/07/11 1H sdh
b Pembuatan disain dan RAB 20/07/11 26/07/2011 20/07/11 8/8/11  12H sdh
III Musyawarah Kabupaten II
a Persiapan Forum 1/08/2011 10/8/2011 1/8/2011 10/8/2011 10H  sdh
b Musyawarah Pendanaan 11/8/2011 11/8/2011 11/8/2011 11/8/2011  sdh
TAHAP PELAKSANAAN
I Persiapan awal pelaksanaan
a Perekrutan & penetapan pengurus bidang TPK Kab 26/07/11 28/07/11 30/07/11 30/07/11 2H
b Pembentukan dan Penetapan Panitia Pengadaan  26/07/11  28/07/11  12/09/11 12/09/11 46H
c Pembentukan dan Penetapan UPKD  26/07/11  28/07/11 11/08/11  11/08/11  14H
II Pelaksanaan Pengadaan Barang dan Jasa
a Pengumuman Pelelangan 28/07/11  08/08/11  03/10/11  07/10/11
b Pendaftaran / Pengambilan dokumen 01/08/11 06/08/11 04/10/11  07/10/11
c Aanwijzing 08/08/11 08/08/11 07/10/11  07/10/11
d Pemasukan Penawaran  09/08/11 11/08/11  11/10/11  11/10/11
e Pembukaan Penawaran 11/08/11 11/08/11  11/10/11 14/10/11
f Evaluasi Penawaran 12/08/11 14/08/11 14/10/11 17/10/11
g Penetapan Pemenang  16/08/11 16/08/11  14/10/11 25/10/11
h Pengumuman Pemenang 18/08/11 18/08/11  21/10/11  26/10/11
i Masa Sanggah 18/08/11 23/08/11 17/10/11 27/10/11  65
j Penunjukan Pemenang 24/08/11  24/08/11 21/10/11 27/10/11  65
k Penandatanganan Kontrak  25/08/11  26/08/11  01/11/11 01/11/11 67
III Rapat Persiapan Teknis  25/08/11  26/08/11 10/11/11 10/11/11  76
IV Pencairan dan Penyaluran Dana  01/09/11  06/09/11 28/09/11 11/11/11 66
V Pelaksanaan Pekerjaan (sub proyek)
VI Sertifikasi pekerjaan (sub projek)
VII Musy. Pertanggung jawaban (Tahap I, II,III)
VIII Musy. Kab. Pertanggungjawaban, serah terima & Alih Kelola
01/08/11

1 Comment

  1. sasli rais said,

    November 3, 2011 at 12:03 pm

    AYO Semangat….AYO kembali ke Optimalisasi


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: