Kab. Poso

Progres Per 15 Agustus 2011

Progres Kegiatan Optimalisasi Kab. Poso Sul teng

No. Uraian Kegiatan JADWAL PELAKSANAAN
Ket.
Rencana [tgl-bln-thn] Realisasi[Tgl-Bln-Thn] Deviasi
Mulai Selesai Mulai Selesai
 TAHAP PERENCANAAN
I Musyawarah Kabupaten I
a Persiapan Forum MKab-I 1/7/11 5/7/11 1/7/11 5/7/11 4 H
Sudah
b Konsolidasi 4/7/11 04/7/11 06/07/11 06/07/11 2 H
sudah
c Forum MKab-I 06/07/11 06/07/11 22/07/11 22/07/11 17 H
Sudah
II Penyusunan Disain dan RAB

a Persiapan (seleksi dan pelatihan) 8/7/11 15/07/11
25/7/11
27/07/11
12 H
Sudah
b Pembuatan disain dan RAB 10/07/11 27/07/11
28/07/11
15/08/11
19
sdh
III Musyawarah Kabupaten II



a Persiapan Forum
25/7/11
28/7/11
12/08/11
15/08/11
sdh
b
Musyawarah Pendanaan 29/7/11
29/7/11
16/08/2011
16/08/2011
 18H sdh
 TAHAP PELAKSANAAN
I Persiapan awal pelaksanaan


a Perekrutan & penetapan pengurus bidang TPK Kab 6/7/2011
6/7/2011 11/7/2011
11/7/2011
5H
 sdh
b Pembentukan dan Penetapan Panitia Pengadaan 5/8/2011
 5/8/2011  ULP ULP

Blm
c Pembentukan dan Penetapan UPKD 6/7/2011
6/7/2011 11/7/2011
11/7/2011
5H
 sdh
II Pelaksanaan Pengadaan Barang dan Jasa
a Pengumuman Pelelangan 11/08/11
15/08/11
07/09/11
15/09/11
 31
b Pendaftaran / Pengambilan dokumen 12/08/11
15/08/11 07/09/11
 15/09/11
 -31
c  Aanwijzing  16/08/11  16/08/11 13/09/11 13/09/11  28
d Pemasukan Penawaran  18/08/11 18/08/11  14/09/11 16/09/11 29
e Pembukaan Penawaran 19/08/11 19/08/11 16/09/11  16/09/11  28
f Evaluasi Penawaran  22/08/11  24/08/11  19/09/11 20/09/11  27
g Penetapan Pemenang  25/08/11  25/08/11 21/09/11  21/09/11 27
h Pengumuman Pemenang  26/08/11 27/08/11 21/09/11 21/09/11 25
i Masa Sanggah 01/09/11 01/09/11 22/09/11 28/09/11 27
j Penunjukan Pemenang  02/09/11 02/09/11 29/09/11 29/09/11 27
k Penandatanganan Kontrak 02/09/11 03/09/11 30/09/11 30/09/11 27
III Rapat Persiapan Teknis 05/09/11  06/09/11  19/08/11 19/08/11  18
IV Pencairan dan Penyaluran Dana  06/09/11 09/09/11 20/09/11  23/09/11
V Pelaksanaan Pekerjaan (sub proyek) 06/09/11 09/09/11 26/09/11   27/09/11
VI Sertifikasi pekerjaan (sub projek)
VII Musy. Pertanggung jawaban  (Tahap I, II,III)
VIII Musy. Kab. Pertanggungjawaban, serah terima & Alih Kelola

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: