Realisasi Tahap Perencanaan Siklus 3

Progres Per 30 Juli   2011

Progres Kegiatan Perencanaan Kec. Siklus 3 SUlteng

No. Kabupaten Desa Realisasi Tahapan Kegiatan (Kecamatan)
DOK SosKec SosDes M.D.P. Keb M.PMD Kajian Teknis M.Reng D. RAB M.dana
Thp I THP 2 THP 3
I Kab.Poso 103
1 Lore Selatan 14 S S B s S S S S S S S
2 Lore Tengah 8 S S B S S S S S S S S
3 Pamona Barat 5 S S B S S S S S S S S
4 Poso Kota 5 S S B S S S S S S S S
5 Poso.P.Selatan 8 S S B S S S S S S S S
6 Poso.P.Utara 7 S S B S S S S S S
S
S
7 Lage 14 S B B S S S S S S S S
8 Pamona Utara 20 S S B S S S S S S S S
5 Pamona Timur 12 S B B S S S S S S S S
II Kab.Tojo Una-una 25
1 Ampana Kota 11 S S B S S S S S S S S
2 Togean 14 S S B S S S S S S S S
III Kab.Banggai 98
1 Toili 25 S B B S S S S S S S S
2 Toili Barat 16 S S B S S S S S S S S
3 Luwuk 21 S B B S S S S S S S S
4 Luwuk Timur 9 S S B S S S S S S S S
5 Bualemo 16 S B B S S S S S S S S
6 Masama 11 S S B S S S S S S S S
IV Kab.Morowali 136
1 Menui.Kep 18 S B B S S S S S S S S
2 Bahodopi 12 S B B S S S S S S S S
3 Bungku Tengah 29 S B B S S S S S s S S
4 Bungku Barat 10 S B B S S S S S S S S
5 Lembo 24 S B B S S S S S S S S
6 Bungku Utara 20 S B B S S S S S S S S
7 Soyajaya 9 S B B S S S S S S S S
8 Mamosalato 14 S B B S S S S S S S S
Prov. Sulteng S 25 17 8 25 25 25 25 25 25 25
25
P
B 8 17

Keterangan :

1. S = Sudah 2. P = Proses 3. B = Belum

Progres Kegiatan Perencanaan Kabupaten. Siklus 3 SUlteng

No. Kabupaten Kec Realisasi Tahapan Kegiatan Kabupaten
DOK SosKab FGD PSS MSS-1a MSS-1b Kajian Teknis M.Reng D. RAB M.dana
Thp I THP 2 THP 3
I Kab.Poso 9 S S S S S S S S S S
S
II Kab.Tojo Una-una 2 S S S S S S S S S S
S
III Kab.Banggai 6 S S S S S S S S S S S
IV Kab.Morowali 8 S S S S S S S S S S S
Prov. Sulteng S 4 4 4 4 4 4 4 4 4 4
P
B

Keterangan :

1. S = Sudah 2. P = Proses 3. B = Belum

Progres Per 30 Juli 2011

Progres Kegiatan Perencanaan Kec. Siklus 3 SUlteng

No. Kabupaten Desa Realisasi Tahapan Kegiatan (Kecamatan)
DOK SosKec SosDes M.D.P. Keb M.PMD Kajian Teknis M.Reng D. RAB M.dana
Thp I THP 2 THP 3
I Kab.Poso 103
1 Lore Selatan 14 S S B s S S S S S S S
2 Lore Tengah 8 S S B S S S S S S S S
3 Pamona Barat 5 S S B S S S S S S S S
4 Poso Kota 5 S S B S S S S S S S S
5 Poso.P.Selatan 8 S S B S S S S S S S S
6 Poso.P.Utara 7 S S B S S S S S S
S
S
7 Lage 14 S B B S S S S S S S S
8 Pamona Utara 20 S S B S S S S S S S S
5 Pamona Timur 12 S B B S S S S S S S S
II Kab.Tojo Una-una 25
1 Ampana Kota 11 S S B S S S S S S S S
2 Togean 14 S S B S S S S S S S S
III Kab.Banggai 98
1 Toili 25 S B B S S S S S S S S
2 Toili Barat 16 S S B S S S S S S S S
3 Luwuk 21 S B B S S S S S S S S
4 Luwuk Timur 9 S S B S S S S S S S S
5 Bualemo 16 S B B S S S S S S S S
6 Masama 11 S S B S S S S S S S S
IV Kab.Morowali 136
1 Menui.Kep 18 S B B S S S S S S S S
2 Bahodopi 12 S B B S S S S S S S S
3 Bungku Tengah 29 S B B S S S S S s S S
4 Bungku Barat 10 S B B S S S S S S S S
5 Lembo 24 S B B S S S S S S S S
6 Bungku Utara 20 S B B S S S S S S S S
7 Soyajaya 9 S B B S S S S S S S S
8 Mamosalato 14 S B B S S S S S S S S
Prov. Sulteng S 25 17 8 25 25 25 25 25 25 25
25
P
B 8 17

Keterangan :

1. S = Sudah 2. P = Proses 3. B = Belum

Progres Kegiatan Perencanaan Kabupaten. Siklus 3 SUlteng

No. Kabupaten Kec Realisasi Tahapan Kegiatan Kabupaten
DOK SosKab FGD PSS MSS-1a MSS-1b Kajian Teknis M.Reng D. RAB M.dana
Thp I THP 2 THP 3
I Kab.Poso 9 S S S S S S S S S S
S
II Kab.Tojo Una-una 2 S S S S S S S S S S
S
III Kab.Banggai 6 S S S S S S S S S S S
IV Kab.Morowali 8 S S S S S S S S S S S
Prov. Sulteng S 4 4 4 4 4 4 4 4 4 4
P
B

Keterangan :

1. S = Sudah 2. P = Proses 3. B = Belum

Progres Per 30 Juli  2011

Progres Kegiatan Perencanaan Kec. Siklus 3 (TA.2010) SUlteng

No. Kabupaten Desa Realisasi Tahapan Kegiatan (Kecamatan)
DOK REV Desain RAB
M.Pend SPC M.Pers
Lelang Plaks M.P I&II
Serti
Thp I THP 2 THP 3
I Kab.Poso 103
1 Lore Selatan 14 S S S s S S S S S S S
2 Lore Tengah 8 S S S S S S S S S S S
3 Pamona Barat 5 S S S S S S S S S S S
4 Poso Kota 5 S S S S S S S S S S S
5 Poso.P.Selatan 8 S S S S S S S S S S S
6 Poso.P.Utara 7 S S S S S S S S S
S
S
7 Lage 14 S B S S S S S S S S S
8 Pamona Utara 20 S S S S S S S S S S S
5 Pamona Timur 12 S B S S S S S S S S S
II Kab.Tojo Una-una 25
1 Ampana Kota 11 S S S S S S S S S S S
2 Togean 14 S S S S S S S S S S S
III Kab.Banggai 98
1 Toili 25 S S S S S S S S S S S
2 Toili Barat 16 S S S S S S S S S S S
3 Luwuk 21 S S S S S S S S S S S
4 Luwuk Timur 9 S S S S S S S S S S S
5 Bualemo 16 S S S S S S S S S S S
6 Masama 11 S S S S S S S S S S S
IV Kab.Morowali 136
1 Menui.Kep 18 S S S S S S S S S S S
2 Bahodopi 12 S S S S S S S S S S S
3 Bungku Tengah 29 S S S S S S S S S S S
4 Bungku Barat 10 S S S S S S S S S S S
5 Lembo 24 S S S S S S S S S S S
6 Bungku Utara 20 S S S S S S S S S S S
7 Soyajaya 9 S S S S S S S S S S S
8 Mamosalato 14 S S S S S S S S S S S
Prov. Sulteng S 25 25 25 25 25 25 25 25 25 25
25
P
B

Keterangan :

1. S = Sudah 2. P = Proses 3. B = Belum

Progres Kegiatan Perencanaan Kabupaten. Siklus 3  (2010)SUlteng

No. Kabupaten Kec Realisasi Tahapan Kegiatan Kabupaten
DOK SosKab FGD PSS MSS-1a MSS-1b Kajian Teknis M.Reng D. RAB M.dana
Thp I THP 2 THP 3
I Kab.Poso 9 S S S S S S S S S S
S
II Kab.Tojo Una-una 2 S S S S S S S S S S
S
III Kab.Banggai 6 S S S S S S S S S S S
IV Kab.Morowali 8 S S S S S S S S S S S
Prov. Sulteng S 4 4 4 4 4 4 4 4 4 4
P
B

Keterangan :

1. S = Sudah 2. P = Proses 3. B = Belum